Building the System: Day 3


E.F. and M. were onsite by 8:45 this morning. Had they not had to wait for a supply shop in Trenton to open they would have arrived even earlier. They took a few minutes to get organized and then started installing the rails on which panels would be mounted.

Before lunchtime they'd carried a few panels up and begun installing them.

Once they found their rhythm the panels were locked down one after another. Their goal was to get the twelve panels mounted on the garage roof today (before tackling the thirty-six that will go on the main roof).

Five down, seven to go.

Just a couple more after this one.

Twelve panels installed -- day 3 mission accomplished.